JPMA has set up sugar and allied industries across the nation. The firm has helped industrialists in all parts of the nation set up small and large plants dealing in production of sugarcane, sugar and by-products. Using new technologies and applications in the production of Raw, Refined, White Sugar manufacturing, Cogeneration of Power and production of Rectified Spirit, Ethanol and Extra Neutral Alcohol, we have helped India become a sugar surplus nation.
UNIT - Shri Datta Sakhar Karkhana, Asurle-Porle
Project Management Consultancy for Expansion of Sugar factory from 2500 TCD to 7500 TCD from 2012 - 2017
UNIT - Expansion of existing Sugar factory from 1750 TCD to 3500 TCD from 2014 - 2017
Project Management Consultancy for Expansion of existing Sugar factory from 1750 TCD to 3500 TCD from 2014 - 2017
UNIT - Project Management Consultancy for expansion of Sugar Factory along with Cogeneration Power Plant in two phases.
Phase I – Expansion from 3500 TCD to 4500 TCD in the year 2014. Cogeneration Power Plant of total capacity 21.5 MW was commissioned in the year 2012
Phase II – Expansion from 4500 TCD to 7000 TCD in the year 2017 Energy Optimization (Energy Audit)
Technical Report for Upgradation of Sugar Plant capacity to 8000 TCD with BH diversion in the year 2021
UNIT - Project Management Consultancy for Expansion of the sugar factory capacity from 3500 TCD to 5000 TCD in two phases.
Phase – 1 : Expansion of Sugar plant up to 4200 TCD in the year 2017
Phase – 2 : Expansion of Sugar Plant up to 5000 TCD in the year 2019
UNIT - Technical Consultant for Rehabilitation and modernisation of sugar factory in two Phases
Phase – 1 : Balancing of plant to 2500 TCD followed by expansion to 3000 TCD in the year 2007- 2009.
Phase – 2 : Expansion of boiling house from 4500 TCD to 5000 TCD in the year 2017 – 2018
Project Management Consultancy services for New Duel feed Ethanol Distillery plant with Syrup and Molasses route processing complex by sugarcane crushing capacity of 3500 tons per day (TCD) and producing required power of 14 MW
Ongoing Project.
Technical Consultant for Sugar Factory Expansion from 4500 TCD to 10000 TCD during 2013-2015
Technical Consultant for Plant performance improvement in year 2015, 2016 and 2017. Identify the bottlenecks for achieving crushing capacity of 18000 TCD, Steam Economy, Improvement of Plant efficiency and reduction in Process losses
UNIT - Greenfield Sugar Plant of capacity 3500 TCD expandable to 5000 TCD with Cogeneration Plant
New Sugar Plant of capacity 3500 TCD expandable to 5000 TCD with Cogeneration Plant,
Project Completed in year - 2015 to 2019.
New Greenfield Jaggery Plant of capacity 300 TCD expandable to 500 TCD (on Going Project)
Relocation of an old sugar Factory from Hindupur in Andhra Pradesh to Munoli in Karnataka. Expansion of Factory from 1500 TCD to 2500 TCD with 12.2-MWe power plant. Expansion of Factory from 3500 TCD with 12.2-MWe power plant
Project Completed in year - 2001 to 2003
Project Management Consultancy for Plant expansion 2750 TCD to 4000 TCD, optimisation for energy economy and improving sugar recovery and Installation of surplus power co-generation plant of 18-MW with exportable power of 13-MW.
Project Completed in year - 2007 to 2009
Project Management Consultancy for New Greenfield Sugar Project Detailed of 3500 TCD (145 TCH) along with 15 MW integrated cogeneration plantt
Plant completed in year - 2010 to 2012
Project Management Consultancy services for Modernization and Upgradation of Balrampur and Babhnan Units
Ongoing Project.
UNIT: - Project Management Consultancy (PMC) Services for Installation of new Milling Tandem and Implementation of Steam Economy Measures at
Unit I
Ongoing Project.
UNIT - Nigohi, Shahjahanpur, Uttar Pradesh
Technical Consultancy for
Technical Consultancy for
Technical Consultancy for
Technical Consultant for Sugar factory from 2012 to till date. JPMA completed following activities successfully
Trouble shooting of evaporator station in the year 2012-2013.
Study and evaluate station wise performance of sugar factory to achieve crushing rate of 6000 TCD in year 2013-2014
Bankable Detailed Project Report (DPR-B) for expansion of sugar plant from 6000 TCD to 11160 TCD including cogeneration Plant in year 2014-2015.
Yearly Annual consultancy Services for Improvement in plant performance and reduce the losses 2013 to 2020
UNIT - Sabitgarh, Uttar Pradesh
Technical Consultancy for
Total turnkey consultancy services for 3500 TCD initial capacity with co-generation Plant right from initial site selection, feasibility study up to final commissioning and performance trials.
UNIT - Technical Consultant for Optimization, balancing and expansion of existing sugar Plant from existing 6250 TCD to 7000 TCD
Technical Consultant for expansion of sugar plant from 2016
UNIT - The Plant was initially 1500 TCD in 1978 and plant expanded from 1500 TCD to 12000 TCD in various stages under the consultancy services of JPMA.
Sugar Plant expansion to 8500 tons of cane per day during 2005-06.
Sugar Plant expansion from 8500 TCD to 10000 TCD during 2006-2007.
Sugar Plant expansion project from 10000 TCD to 12000 TCD during 2010-2012.
Consultancy services for providing Transaction Advisory (TA) services for selection of Executive Agency (EA) for shifting of Faridkot Sugar Mills Plant & Machinery to Bhogpur Sugar Mills along with installation, commissioning & supervision, O & M services.
Final Capacity of Bhogpur plant after shifting of Faridkot Sugar Mills is 3000 TCD & 15 MW Cogeneration.
Project Commissioned in the Year 2021.
Detailed Project Report (DPR) for Expansion and stabilization of Sugar Plant to 7500 TCD
Feasibility Study Report (FSR) for converting existing Grain Based Distillery to Dual Feed Distillery and installation of VInasse Dryer at parallel 60 KLPD Grain Based Distillery
Feasibility Study Report (FSR) for setting up New 100 KLPD Dual Feed Distillery Plant
Project Completed in March 2021
Asset valuation of 20 MW Cogeneration Plant
Asset valuation of 4000 TCD Sugar Plant with 13.15 MW Cogeneration and 30 KLPD Distillery
Project Completed in March 2021